| Classification |
Units of Work |
|
| CCC |
ERA |
| 110 Cabin |
1 |
|
Frame Construction 28'8" x 21'8" three rooms |
| 110 Residence |
| 1 |
Remodel frame messhall into 22' x 44' three-room dwelling |
| 110 Employee's Dormitory |
| 1 |
Constructed according to Master Plan No. BC-3014E and working
Plan No. BC-327 B most of the material being salvaged from other
buildings |
| 113 Comfort Station |
2 |
|
Removed from campground and relocated and remodeled |
| 113 Comfort Station |
1 |
|
Log construction 13'6" x 24', two compartment |
| 113 Pit Toilets |
3 |
|
4' x 5' frame construction |
| 113 Pit Toilets |
2 |
|
6'6" x 5'6" native lumber for two occupants |
| 115 Lookout-Rainbow Point |
1 |
|
17'6" x 52' log construction, open front. Exhibit case back wall |
| 120 Contact Station |
1 |
|
Log construction 7' x 10'6" located on island 200' x 11' for landscaping |
| 120 Move Messhall |
1 |
|
Move building in sections and reassemble into five-room dwelling 23' x 44'7" |
| 131 Boundary Fence |
3204 rods | 8.4 miles |
5 strand barb wire cedar posts 10' spacing |
| 134 Powerline |
3.2 miles | .5 miles |
Set posts for 7250 volt line in cooperation with Garkane Power Company, 1 mile of line in park |
| 139 Sanitation Improvement |
| 1 |
Excavating garbage pit 20' x 60' x 10' |
| 139 Sewerline |
700 linear feet |
|
6" vitrified clay pipe |
| 139 Sewer System |
1 |
|
2800' vitrified clay pipe - 10 manholes connects to National Park System |
| 140 Telephone lines |
1.9 miles |
|
Relocation of telephone lines to new location |
| 141 Drinking Fountains |
2 |
|
Rock Masonry pedestal 3'6" high |
| 143 waterline |
2300 linear feet |
|
1100'- 2" galv. pipe 200'- 1" galv. pipe, 600'- 3/4" galv. pipe |
| 148 Fireplaces |
20 |
|
Rock masonry in accordance with standard plans. |
| 149 Cattle Guard |
1 |
|
8' x 22'25' rails space 6-3/4" 8' underpass with 8'9" clearance reinforced concrete walls and beams |
| 149 Cattle Guard |
1 |
|
28'2" x 9'1" tread 40" rail concrete abutments |
| 153 Road Signs |
23 |
|
Yellow pine carved directional signs average 1'4" high. Posts yellow pine peeled and treated 3' high. |
| 153 Monuments |
1 |
|
Treated peeled yellow pine pillar 10' high supporting 8' x 4'9" entrance sign, 4'5" yellow pine pillar opposite |
| 155 Tables |
35 |
|
Table and bench combination in accordance with standard plans |
| 155 Campground tables |
51 |
|
Standard design, frame construction |
| 157 Lecture Circle |
1 |
|
Gravel surface, permanent log seats, timber platform with firepits |
| 157 Miscellaneous Minor Improvements |
1 |
|
Constructed museum exhibit cases |
| 157 Fire Danger Weather Station |
1 |
|
20' squared fenced enclosure housing hydrothermograph, fuel, moisture instruments and wind gauge, and specmeter |
| 202 Minor Roads |
3.05 miles |
|
18' graded and graveled surfaced |
| 206 Foot Trails |
16 miles |
|
.6 miles4' gravel surface |
| 206 Trail Improvement |
| 12.5 miles |
Reconditioning sections of trail widening to 4' |
| 207 Horse Trails |
45.2 miles |
|
4' earth graded |
| 304 Check dams |
1000 |
|
1' to 5' permanent log check dams |
| 603 Roadside Cleanup |
7 miles |
|
Remove dam timber, etc., on roadsides |
| 609 Insect Pest Control |
20745 acres | 23100 acres |
Spotting and treating acres beetle infected yellow pine and Douglas Fir |
| 705 Landscaping |
51 acres |
|
Dressing and stabilizing road slopes |
| 706 Moving and planting trees and shrubs |
250 | 1150 |
Moving and planting native trees and shrubs around campground |
| 710 Parking Areas |
2250 square yards |
|
300 square yards graded and gravel surfaced with rock masonry barrier, 1950 square yards with log barrier |
| 711 Campground Development |
.6 acres |
|
Grading and surfacing for future development |
| 713 Razing Undesirable Structure |
1 |
|
Demolish and salvage of old contact station |
| 713 Demolish Old Dormitory |
| 1 |
Demolish building and salvage all usable material |
| 713 Obliteration of Old Roads |
| 4 miles |
Change areas to original state with rock, trees, and brush |
| 716 FootpathsRainbow Point |
200 linear feet |
|
6' path with 1/2" gravel surface |
| 1004 Wood Eradication |
14 acres |
|
Eradication of poisonous and exotic weeds and plants |
| 1012 Preparation and Transfer of Materials |
55,458 F.B.M. |
|
Windthrown logs salvaged and sawed into lumber |
| 1012 Preparation and Transfer of Materials |
84 logs |
|
12', 14', and 16' lengthsaverage 24" diameter, salvage from insect control work |
| 1012 Salvage Beetle Timber |
94,000 F.B.M. |
|
Salvage beetle infected timber which was sawed into lumber for future CCC use |
| 1012 Stockpile-Road Maintenance |
4500 Cubic Yards |
|
Road material for highway maintenance |
| 1023 Lineal Survey |
50 miles |
|
Surveys throughout the park |
| 1025 Topographic Surveys |
35 A |
|
Surveys throughout the park. |